Skyway Bridge to be completely closed to traffic from 9 p.m. on Aug. 3 until 6 a.m. Aug. 4

A Google map screen shot of the Bay of Quinte Bridge which links Hastings to Prince Edward County.

The Bay of Quinte Skyway Bridge will be completely closed to traffic from 9 p.m. on Aug. 3 until 6 a.m. Aug. 4

During this time period the highway will be closed, and no traffic will be permitted to pass over the bridge. This closure is intended for the implementation of staging configuration for Segment D work which will consist of relocating temporary concrete barriers, temporary energy attenuators, delineators and placing temporary pavement markings.

The working area will be shifted to the southbound traffic lane and the active traffic lane will be shifted to the northbound lane.